221
MPP-251
Prepare specifications for the PM analysis module LHC T. Levens, C. Hernalsteens, M. Gasior
220
MPP-245
Document the interlock implementation in an ECR LHC T. Levens
219
MPP-245
Christoph will follow-up with Victor regarding the preparation of the checklists LHC C. Wiesner
218
MPP-244
BI will trigger the necessary actions with the BIS team after they deploy the latest firmware LHC M. Gasior, BIS Team
217
MPP-243
Verify with the FLUKA team if the TCL4-5 could be further open to benefit ARP LHC F. Van der Veken
216
MPP-242
Report to the MPP regarding the decision on the TSU renovation and the outcomeof the reliability analysis or the new interface between BIS and TSU LHC N. Voumard, P. Van Trappen
215
MPP-242
Report on the first experience with beam regarding the reduced sensitivity of the newly installed BLMs and propose the interlocking strategy for the 2024 run LHC B. Salvachua
214
MPP-240
CCR describing changes in LBDS remote validation feature LHC C. Boucly, N. Magnin
213
MPP-240
Update BCCM commissioning procedure LHC C. Hernalsteens, M. Gasior
212
MPP-240
ECR describing the changes in SPS SMP-BCT changes in YETS 23/24 LHC R. Secondo, T. Levens
211
MPP-239
COLLWG
Compare expected 28 kW losses to the HiRadMat tests LHC A. Lechner
210
MPP-238
Validate all the collimator segments from 120cm to 60cm (and all the matchpoints in between) to ensure safe fast beta* levelling to 60cm LHC R. Bruce
209
MPP-237
Implement a way to limit the crossing angle change around the reference value LHC M. Hostettler
208
MPP-237
Share the outcome of the modifications and BIC validation with the MPP LHC M. Milovanovic
207
MPP-236
COLLWG
Share a 3D model of the foil shape (V. Coco) and perform impedance simulations LHC B. Salvant
206
MPP-236
COLLWG
Proposal for the post TS1 ramp-up and for the documentation of the VeLo-related checks LHC C. Wiesner
205
MPP-235
Prepare an ECR to document the changes LHC T. Levens
204
MPP-234
Define the filling schemes corresponding to each intensity step LHC C. Wiesner, F. Moortgat
203
MPP-234
Determine the interlock level for the TCT BPMs for the 2023 configuration LHC BE-OP, Collimation
202
MPP-234
Define the optics steps at which the measurements will take place and agree with OP for a slot to perform them LHC BE-OP, C. Hernalsteens
201
MPP-233
COLLWG
Report to the MPP on the design of the new safety system LHC TE-VSC
200
MPP-233
COLLWG
Determine limits on the loss rate that can be tolerated for local aperture measurement LHC LHCb
199
MPP-232
Validate collimator settings for B* levelling 2023 scenario LHC M. Hostettler, Collimation
198
MPP-232
Provide a proposal for checks on collimator interlock settings LHC M. Hostettler
197
MPP-232
Verify PM trigger of the BCCM system before making it operational LHC M. Gasior, C. Wiesner
196
MPP-232
MPS procedure for TOTEM (and similarly for CTPPS and ARP) LHC M. Deile, C. Hernalsteens
195
MPP-232
Provide a procedure to OP for FMCM triggering tests LHC A. Antoine, J. Wenninger
194
MPP-232
Decide if blindable BLMs should be commissioned in 2023 LHC D. Wollmann, C. Bracco, B. Salvachua
193
MPP-231
Draft ECR on the proposed DC-BCT and SMP changes for the SPS LHC T. Levens, R. Secondo
192
MPP-222
Check the aperture limits of the new BSRTM device are in accordance with Run3 parameters LHC R. De Maria, D. Mirarchi
191
MPP-222
Provide semi-flat functions to test 2023 Beta* levelling mechanics in 2022 without interfering with levelling LHC M. Hostettler, D. Mirarchi
190
MPP-223
Confirm the length of the ADT excitation window in terms of number of bunches LHC C. Hernalsteens
189
MPP-223
Identify and solve the BLM XPOC issue LHC C. Zamantzas
188
MPP-223
Report on the validation of the diode solution for the LSS3 BLMs issue LHC C. Zamantzas
187
MPP-223
Follow-up on the protection of settings for the SPS MKE phasing and discuss the potential impact of rolling back with LSA tags on other critical settings LHC MPP, BE-OP
186
MPP-224
COLLWG
Follow -up on the delay of the beam dumped event sent out over the timing system LHC G. Kruk
185
MPP-224
COLLWG
Install a BLM close to the BSRTMB in IR4 during the YETS LHC B. Salvachua
184
MPP-224
COLLWG
Define the list of required loss maps for critical scenario LHC BE-OP, Collimation
183
MPP-224
COLLWG
Define and organize a test with beam to confirm that the beam is not affected in case of an abort of the wire power converter during the timeframe of the interlock reaction time of the WIC and BIS LHC BE-OP, BE-ABP
182
MPP-226
Follow-up on the RBAC protection of the settings of machine protection equipment LHC MPP
181
MPP-227
Perform all BBWC tests to allow the powering of the wires during the ramp-up once the software is ready LHC G. Sterbini
180
MPP-229
By the end of the year inputs for potential additional interlocks or hardware stops for the protections of components in the FRAS must be provided by the relevant teams and collected for the FRAS specifications LHC F.-X. Nury
179
MPP-229
Prepare detailed specifications for the interlocks, including the FRAS key in CCR and the newly discussed “FRAS powering interlock” to a maskable input of the CIBUs in IR1 and 5 LHC FRAS, MPP
178
MPP-230
Report on the currently tested options to minimize the bunch length dependence of the BCCM signals LHC M. Gasior
177
MPP-220
Analyze the changes to be made in the test procedure and study the consequences LHC L. Roy, MPP
176
MPP-220
Provide the list of disabled BIS channels to the MPP and inform the MPP once the channels are enabled again LHC C. Martin
175
MPP-220
Implement the publication through FESA of the additional signals (threshold values and measured value) and update the EDMS document LHC M. Di Castro
174
MPP-208
Draft a procedure for the tracking of the bypassed equipment PBS J. Uythoven
173
MPP-208
Organize a meeting between OP and the MPE SW team to define the specifications for an improved GUI PBS B. Mikulec
172
MPP-218
Review the inconsistency that the WIC will not interlock the beam in case of a power converter failure, but still interlock the beam in case of a magnet failure PBS G.P. Di Giovanni, MPP, D. Nisbet
171
MPP-218
Update the ECR and circulate it for approval PBS G.P. Di Giovanni
170
MPP-211
Implement the proposed operational limits for the ADT excitation LHC D. Valuch
169
MPP-211
Obtain more inputs on the possibility of a cold weld from EN-MME LHC J. Uythoven
168
MPP-211
Perform opening test with the velo before the LMC, including video LHC F. Sanders
167
MPP-211
Propose a proper timeline for a possible replacement scenario LHC F. Sanders
166
MPP-213
Study necessity and feasibility of special interlock configuration for LINAC4 3 MeV runs Linac4 P. Skowronski
165
MPP-213
Initiate study of alternative interlock configuration and failure diagnostics for Linac4 and possibly other injectors Linac4 P. Skowronski
164
MPP-213
Organise discussion about changing RF to HV as actuator for the source BIC and report back to the MPP Linac4 D. Nisbet
163
MPP-213
Update BIS specification (page 2) clarifying present and future situation wrt RF actuator Linac4PSB C. Martin
162
MPP-213
Update specifications “Logic for SIS Software Verification of LEBT Parameters” and send around for approval Linac4 R. Scrivens
161
MPP-214
Update the BLM machine protection commissioning procedure with tests to ensure that the “beam info” bypass devices are removed prior to operation LHC B. Salvachua, C. Zamantzas
160
MPP-214
Communicate the list of variable names (for NXCALS) that are needed to assess the latency of the full chain LHC J. Uythoven
159
MPP-214
Ensure that the issues currently requiring the masking of XPOC are resolved before declaring stable beams LHC N. Magnin
158
MPP-215
Verify high pileup implications Linac4 A. Lombardi
157
MPP-217
Verify high pileup implications LHC F. Moortgat
156
MPP-217
Circulate the BCCM procedure LHC M. Gasior
155
MPP-217
Circulate the BPF procedure LHC R. Secondo
154
MPP-217
Update SMP procedure and add that the BPF checks after each injection are done implicitly by the BIS LHC R. Secondo
153
MPP-217
Include BPF tests in the SMP IPOC procedure LHC R. Secondo
152
MPP-209
Add ARP interlock checks to the checklist based on previous EDMS documents LHC C. Hernalsteens, I. Lopez
151
MPP-209
Plan interlocks tests (basic interlock functionalities for each pot and comprehensive test in a dry run with changing beam modes and flags) LHC BE-OP, M. Deile
150
MPP-209
Add TOTEM/CTPPS interlock tests to the checklist LHC C. Hernalsteens, M. Deile
149
MPP-209
Discuss the handling of the redundant energy and beta* limits and propose possible improvements LHC Collimation, BE-OP
148
MPP-209
Circulate a list of people for check and approve the EDMS procedure LHC C. Hernalsteens
147
MPP-209
Give administrator access to MPP representatives and user access to the people who will fill in the results, verify with each system representative LHC C. Hernalsteens
146
MPP-210
Define and create checklist tests for collimation, BLMs and the RF system LHC J. Wenninger, H. Timko, C. Hernalsteens
145
MPP-207
Decide if a filter on the signal of the BLMs behind the dumps is needed to avoid saturation LHC C. Wiesner, A. Lechner, Y. Dutheil
144
MPP-207
Evaluate feasibility of porting UFO Buster data acquisition from SDDS files to Post Mortem LHC A. Lechner, J.C. Garnier, C. Zamantzas
143
MPP-207
Add TDE N2 pressure interlock gauges to SIS following LS2 updates LHC J. Wenninger
142
MPP-207
Evaluate feasibility of implementing interlock based on the correct transfer line optics ID generated by SIS LHC J. Wenninger
141
MPP-207
Check if the Beta* and energy gap interlock functionality is implemented in the TCDIs LHC Y. Dutheil
140
MPP-207
Check if energy extraction switches opening signal sent from SIS is correctly received by the CIRCUIT SCADA LHC J. Wenninger, A. Antoine
139
MPP-206
Add commissioning of blindable BLMs to the injection procedure LHC Y. Dutheil
138
MPP-206
Release AGK commissioning document in EDMS and link to MPP tree LHC Y. Dutheil
137
MPP-205
Coordinate with C.Martin (TE-MPE-MI) to verify CIBU connections of the vacuum system LHC G. Pigny
136
MPP-205
Validation of automatic script for the vacuum checkout tests LHC G. Pigny
135
MPP-204
Update PIC commissioning procedure (EDMS-896390) with the validation of the new current dependent GPM function, including coupling the tests of RB and RQ circuits LHC A. Antoine
134
MPP-201
Update signal names for N2 pressure gauges interlocked in the SIS and re-establish the SIS injection interlock on too low N2 pressure LHC J. Wenninger, M. Di Castro 2021-08-31
133
MPP-198
Operation of LHCb velo at 450 GeV: Estimate the available aperture for a velo closing at 450 GeV in collaboration with optics and collimation teams and propose the measurement of the aperture in IP8 at injection before any physics operation at injection LHC V. Coco 2021-03-31
132
MPP-198
LHCb velo motion system: Implement signal from limit switches to the VSS LHC X. Pons 2021-03-31
131
MPP-198
LHCb velo motion system: Prepare a detailed procedure for manual movement and perform the procedure in full when the detector is installed with active control system to monitor the movement and avoid damage to the limit switches LHC V. Coco, F. Sanders 2021-03-31
130
MPP-198
LHCb velo motion system: Evaluate if a warning could be produced if the VELO alignment algorithm attempts to move one side beyond the 0 mm point LHC V. Coco 2021-03-31
129
MPP-198
LHCb velo motion system: Prepare a specifications document for the motion control, failures and interlocks LHC X. Pons 2021-03-31
128
MPP-179
Evaluate how the masking of watchdog interlocks in the SIS can be only allowed for short pulse lengths Linac4 B. Mikulec 2021-04-30
127
MPP-181
Clarify the current settings of the SMP min/max beta* values LHC R. Secondo, J. Wenninger
126
MPP-181
Add follow-up list from MPP workshop to MPP website and schedule MPP meetings on the different topics LHC MPP
125
MPP-181
Formalize the list of alternate members for the rMPP and update e-groups and slides on Indico LHC C. Wiesner, M. Zerlauth
124
MPP-188
Clarify if the central values of LEBT settings should be stored as LSA virtual parameter to allow them to be read out by the foreseen sequencer task, taking into account the experience of similar applications in the injectors Linac4 B. Mikulec, R. Scrivens
123
MPP-188
Review the specifications for the Linac4 sequencer task for switching to the low-intensity mode (EDMS L4-C-PRD-0001) in order to ensure coherence with the new “Logic for SIS Software Verification of LEBT Parameters” (EDMS L4-CIB-ES-0007) Linac4 B. Mikulec, R. Scrivens
122
MPP-188
Evaluate RF interlocking and recovery procedure based on the experience from the Linac4 commissioning and early operation and report the results to the MPP Linac4 R. Wegner
121
MPP-201
Implement additional software threshold for maximum losses during the slow extraction SPS M. Fraser, V. Kain
120
MPP-201
Add position IN switches to the TECS hardware interlock SPS M. Di Castro
119
MPP-201
Add position IN switches to the TECS hardware interlock SPS M. Di Castro
118
MPP-201
Prepare and organize review of the SPS slow extraction system SPS MPP, TE-ABT, BE-OP
117
MPP-200
Propose how to protect the CTRB interface of the BLMs to the timing system against accidental changes and overwriting via FESA, in collaboration with the timing team Linac4PSBPS J. Uythoven, S. Jackson
116
MPP-199
Discuss with equipment owners and OP in Linac4, PS and PSB if the 1.2s delay can be removed for the injectors upstream of the SPS and decide when this change can be implemented and update the specification accordingly Linac4PSBPS J. Uythoven, R. Mompo 2021-11-30
115
MPP-197
Organize a discussion on the BIS GUI for the injectors PSB J. Uythoven
114
MPP-197
Circulate the information on the non-conformities to the MPP representatives for the different equipment LHC J. Uythoven, D. Wollmann
113
MPP-197
Verify how the connection has been done between POPS-B and BIS and describe the user input to BIS PSB F. Boattini
112
MPP-196
Verify the maximum allowed XRP temperature with TE-VSC, taking into account outgassing and the temperature of the ferrites LHC M. Trzebinski
111
MPP-195
COLLWG
Study the option of using the space in UJ76 during Run III LHC M. Gasior, T. Levens
110
MPP-195
COLLWG
Determine a strategy for P8 LHC Collimation, R. Bruce
109
MPP-195
COLLWG
Circulate a list of expected redundancies for run III LHC Collimation, R. Bruce
108
MPP-195
COLLWG
Check orbit at the crystal during injection failure LHC Collimation
107
MPP-195
COLLWG
Produce detailed operational scenarios and required validation for the use of the crystals LHC Collimation
106
MPP-195
COLLWG
Produce commissioning procedure for the crystals LHC Collimation
105
MPP-195
COLLWG
Check the angle change at the crystal during 10Hz orbit oscillations LHC Collimation
104
MPP-193
Evaluate the potential gain and feasibility of evaluating the beam orbit at the collimator BPMs before starting the ramp-up of the BBLR wire current and issuing a warning if required LHC G. Sterbini, S. Radaelli, J. Wenninger
103
MPP-193
Evaluate together with the LPC the potential effect of BBCW operation on luminosity and luminous region LHC Y. Papaphilippou, G. Sterbini 2021-05-01
102
MPP-193
Update and circulate the procedure for “BBCW Commissioning and Revalidation after Failure Recovery” and then upload it on EDMS for approval LHC A. Rossi
101
MPP-193
Propose safe and reliable solution to force the BBCW user input to the WIC to TRUE in order to resume beam operation without BBCW LHC A. Rossi, R. Mompo
100
MPP-193
Confirm revalidation procedure for the BBCW after loss of collimator coolant LHC A. Rossi, M. Di Castro
99
MPP-193
Define required qualification tests for the BBCW after a TS and YETS LHC A. Rossi
98
MPP-193
Review the necessity to keep the existing SIS interlock on the BBCW PC current LHC A. Rossi, J. Wenninger 2021-05-01
97
MPP-193
Reassess the temperature load on the BPMs in both TCSP jaws in case of an asynchronous beam dump considering the worst-case (type 2) erratic LHC F. Carra, A. Lechner 2021-06-30
96
MPP-193
Update expected energy deposition based on the newest FLUKA studies for the case of an asynchronous beam dump and an injection error for the relevant collimator materials LHC F. Carra, A. Lechner 2021-06-30
95
MPP-194
Update and approval of the procedure for injection without stripping foil (EDMS 2370098) following the comments from the MPP PSB B. Mikulec
94
MPP-186
Evaluate if automatic checks of the internal performance of the SPS BIS systems are required SPS J. Uythoven
93
MPP-186
Discuss with the MD coordinators for all the injector chain the role of rMPP in the preparation of machine protection critical MD SPSPSPSBLinac4 J. Uythoven
92
MPP-186
Verify the acceptance of the proposed members to be part of the rMPP for injectors, for those not present at the meeting SPSPSPSBLinac4 J. Uythoven
91
MPP-186
Present the extension of the rMPP mandate to the injectors to the IEFC SPSPSPSBLinac4 J. Uythoven
90
MPP-186
Update specifications of the MDSH PC SPS D. Nisbet
89
MPP-186
Update specifications for the SPS and TT10 WIC with the modified MDSH connections SPS R. Mompo 2021-06-01
88
MPP-186
Update the specifications for the SPS Injection BIS with the new “MKP enabled” input to the TT2-TT10 slave BIC SPS I. Romera
87
MPP-186
Update commissioning procedure and checklists for injection tests with new MDSH functionality SPS V. Kain, BE-OP
86
MPP-186
Install new connection “MKP enabled” from the MKP to the TT2-TT10 slave BIC PSSPS I. Romera, TE-MPE-MI
85
MPP-189
Study how to implement an online optics model and related configuration management depending on the optics Linac4 B. Mikulec, R. Scrivens
84
MPP-184
Propose RBAC roles for Machine Critical Settings at LINAC4/PSB for implementation as soon as reasonable Linac4PSB B. Mikulec
83
MPP-182
Define procedure under which circumstances and how to change the high-loss LINAC4 watchdog limits, including roll back to standard operation Linac4 A. Lombardi 2021-04-30
82
MPP-182
Write procedure for injection into less than four PSB rings PSB B. Mikulec
81
MPP-182
Make proposal for the decision-taking process of masking critical interlock channels Linac4PSB J. Uythoven
80
MPP-182
Investigate and if possible implement the link between BIS and External Conditions. Otherwise, implement link via SIS Linac4PSB B. Mikulec, G. Kruk
79
MPP-182
Update the ECR on “PSB External Conditions for Post-LS2”, removing the WIC connection to the EC PSB M. Serano
78
MPP-182
Update the LINAC4/PSB specification of the BIS, replacing the input from the External Conditions LHC C. Martin
77
MPP-181
All groups and teams should verify their proposed MPP representative and inform Christoph and/or Jan if they have comments or suggestions LHC MPP
76
MPP-179
Organise pre-discussion on LINAC4 Caesiation Linac4 J. Uythoven
75
MPP-179
Check feasibility of implementing absolute watchdogs thresholds in hardware (i.e. lost number of particles/charges), which are not scaled with the pulse length Linac4 B. Mikulec, F. Roncarolo
74
MPP-179
Identify relevant locations and beam parameters for energy-deposition studies at LINAC4 Linac4 B. Mikulec, A. Lechner, A. Lombardi 2021-04-30
73
MPP-179
Propose values for BLM hardware settings PSB B. Mikulec 2021-04-30
72
MPP-179
Evaluate if there are additional aperture bottlenecks, where damage might lead to longer downtime than required for a bellow replacement Linac4 A. Lombardi 2021-04-30
71
MPP-179
Evaluate best implementation to send automatic reminders of all active SIS masks for every shift PSB B. Mikulec 2021-04-30
70
MPP-179
Check a) the possibility of using RBAC roles for the change of non-MCS settings and b) the feasibility of using the existing MCS framework, which automatically includes RBAC-role handling, to protect the virtual settings PSB B. Mikulec
69
MPP-179
Write down technical specifications and implementation for the signals migrated to the new timing-system functionality (PSB/PS) PSBPS B. Mikulec
68
MPP-179
Write down technical specifications and implementation (including list of concerned signals) for the consolidated External Conditions PSBPS B. Schofield
64
MPP-192
Report on the first operational experience of the SPS BLM system after LS2 LHC SY-ABT, BE-OP 2021-11-30
63
MPP-191
IQC application and future development: Add an update of the IQC settings for abort gap keeper settings changes LHC SY-ABT, BE-OP
62
MPP-191
IQC application and future development: Discuss the use cases and give inputs for the FESA/firmware preparation for the new dBLM readout electronics LHC J. Wenninger, E. Calvo
61
MPP-191
iBPMs layout in Run3: Propose criteria for iBPM validation before switching to the new system (performance / specifications / reliability criteria) LHC A. Boccardi
60
MPP-191
iBPMs layout in Run3: Discussion on iBPM firmware and possible failure cases LHC A. Boccardi
59
MPP-191
AC-dipole operation with three bunches: Check the interlocking with triplet BLM for 1 pilot and for 3 pilots LHC OMC, R. Tomas, Collimation
58
MPP-191
AC-dipole operation with three bunches: Prepare a procedure for use of 3 bunches after first optics optimization for OMC measurements LHC OMC
57
MPP-191
AC-dipole operation with three bunches: Propose a solution for the introduction of a separate SMP equation for OMC operation with 3 pilot bunches (4E10 protons) LHC J. Uythoven, TE-MPE-MI
56
MPP-187
Study the effect of the modified MKB waveforms on the flashover failure scenario LHC Y. Dutheil, A. Lechner, TE-ABT, EN-STI 2021-06-30
55
MPP-187
Based on first operational experience after LS2, review the steering procedure and evaluate the possibility of steering with full trains LHC C. Bracco, TE-ABT 2022-04-30
54
MPP-187
Investigate the implementation of a SIS based interlock of the integrated intensity of consecutive bunches. Define the maximum number of bunches that have to be taken into account for averaging the bunch intensity LHC J. Wenninger, BE-OP, MPP 2021-08-31
53
MPP-185
Analyse if a limit in the number of consecutive dumps or a minimum time between the dumps is required for Run3 operation LHC M. Calviani, C. Bracco, EN-STI, TE-ABT 2022-07-31
52
MPP-185
Decide if hardware interlock possibilities for the permanent mechanical displacement of the dump have to be foreseen LHC M. Calviani 2022-07-31
51
MPP-185
Verify available resources to implement the new orbit interlocking during LS2 LHC J. Wenninger
50
MPP-183
Update and finalise functional specifications and commissioning procedure for the BCCM, including adaptability of loss threshold settings LHC D. Wollmann, M. Zerlauth, TE-MPE, M. Gasior, BE-BI
49
MPP-183
Specify required data (window size and number of points per integration window) to be sent from the BCCM to Post Mortem, and evaluate feasibility to implement automatic check of BCCM trigger in BIS IPOC LHC J.C. Garnier 2021-03-31
48
MPP-183
Update the Functional Specifications of the SMP with the currently used beta* limits LHC R. Secondo
47
MPP-177
Evaluate feasibility and implications with OP and CO to include an 'MD mask' level in the SIS LHC J. Wenninger, BE-OP
46
MPP-177
Include crystals into recovery sequences for Run 3 and integrate crystals into collimator fixed displays LHC S. Radaelli, BE-OP 2021-11-21
45
MPP-177
Specify line of responsibility for the BBCW temperature interlock for commissioning and operational follow-up LHC S. Radaelli, A. Rossi, BE-BI
44
MPP-177
Repeat response-time measurement with FGC2 system and report results in an AOB at the MPP LHC R. Mompo
43
MPP-176
Write commissioning procedure for the BBCW with and without beam, including reliable check of the wire polarities LHC A. Rossi
42
MPP-176
Measure delay time of the interlock chain for the BBCW, including a WIC unit, in case of a PC trip LHC TE-MPE-MI
41
MPP-176
Write specification for the temperature interlock logic and the filtering of the unphysical temperature sensor readings in the LHC collimator jaws and cooling circuits, and implement them after acceptance LHC M. Di Castro, EN-SMM 2021-06-30
40
MPP-175
Evaluate and define damage limit for SPS beams, based on FLUKA studies if required. Provide the limit as input for BI SPS BE-OP-SPS, K. Li
39
MPP-175
Check status and proper functioning of the SPS BPM interlocks and their connection to the BIS SPS BE-OP-SPS, K. Li
38
MPP-174
The functional specifications for the new CO2 cooling safety system have to be written down, including the expected pressure increase and reaction time as well as the expected consequences and required switches and interlocks LHC LHCb, TE-VSC
37
MPP-174
Clarify who is using the beam mode UNSTABLE BEAMS and what implications it would have to remove it. If removed, it should be removed consistently in all the experiments LHC BE-OP, J. Wenninger
36
MPP-174
Review new movement control and interlocking logic/implementation in fourth quarter 2019 LHC MPP, X. Pons, LHCb
35
MPP-174
Clarify procedure for manual retraction of the VELO and for yearly testing of its functionality LHC LHCb
34
MPP-169
Test steps of the emergency dump procedure related to the LBDS after TS2 LHC M. Solfaroli, N. Magnin 2021-11-30
33
MPP-169
Request functionality to open up excitation window of ADT and prepare OP sequence for scraping the full LHC beam LHC D. Valuch, MPP
32
MPP-163
Prepare a summary slide to show which parameters are checked and how, referring to the AOB - Abort Gap Keeper - protection of fine delay parameter LHC J. Wenninger
31
MPP-161
The TDE pressure interlock should be masked with the new expert mode and unmasked when needed; the injection veto interlock will not be touched LHC J. Wenninger
30
MPP-161
Verify with MP3 if a SIS interlock on DFB temperature is required or if it is sufficient to take care of this via procedures LHC MPP
29
MPP-160
Send schematics of interlock to MPE to verify the interlock card and if re-testing is required LHC A. Rossi
28
MPP-157
Check on redundant powering of the LBDS (UPS test) LHC TE-ABT
27
MPP-157
Request from the impedance team an official statement on the use of the crystal chamber with ion physics beam LHC Collimation
26
MPP-157
Include into the BLM disabling rules a restriction for IPQs in LSS that BLMs in position 2 and 3 are not disabled at the same time LHC E. B. Holzer
25
MPP-156
Define use cases for the DOROS BPMs in IR7 collimators LHC Collimation
24
MPP-155
Operational scenarios and bunch intensities, beam types to be considered for the new BPMs electronics for IR6 LHC BE-OP, MPP
23
MPP-152
Verify the phase advances from the MKDs to the TCPs and how many bunches can escape the TCDQ if injected the abort gap LHC SY-ABT, Collimation
22
MPP-151
Summarize planned changes in the BLMs around the TDEs in an ECR LHC SY-ABT, SY-BI 2021-08-31
21 Verify expected beta beating at critical elements like TCTs or IR6 dump protection in case of a CLIQ mis-firing LHC B. Lindstrom
20 Investigate whether it is needed to implement a smoother change of the tolerance during squeeze instead of going from 4 to 1 sigmas at the end LHC BE-OP-LHC, Collimation
19
MPP-149
Review other failure cases for RD1 and estimate the associated FMCM signals LHC TE-MPE-PE
18
MPP-146
Study the feasibility of a variable window for PC interlocking LHC TE-EPC
17
MPP-145
Produce procedure to be performed after any change of the AGK length LHC N. Magnin 2021-06-01
16
MPP-143
BLM inhibit in case of too high transverse losses with injection: propose commissioning test to verify functionality LHC BE-BI, SY-ABT 2021-04-15
15
MPP-143
BCCM: Make post mortem data operational for BCCM and reduce BCCM trigger levels for all running sums during the beam commissioning to fully exploit the experience from loss maps etc. LHC BE-BI
14
MPP-139
Provide input to Christos concerning testing the BLM reaction time at 450 GeV and top energy in case of a RD1, RD34 powering failure LHC MPP
13
MPP-137
Organise a circulating checklist with points to be followed up between the CC team and MPP; iterate during a coffee discussion early January LHC CC team, MPP
12
MPP-133
Verify which vacuum valves closed during the 2/9/16 MKI erratic LHC TE-ABT
11
MPP-133
Further understand the quench of Q2 during the 2/9/16 MKI erratic LHC BLMTWG, MP3
10
MPP-125
Discuss how to check the status of the BCT buffer. Evaluate the new IQC module to see how often the SPS BCT buffers jump to zero LHC M. Pojer
9
MPP-124
Confirm number of extra bunches the IP7 collimators can take during a type 2 erratic and if this causes a problem LHC R. Bruce
8
MPP-119
Conduct systematic simulation studies on beam scraping by collimators in case of non-working dump LHC M. Solfaroli, M. Valette
7
MPP-119
Discuss the implementation of a passive beam presence flag LHC M. Solfaroli, M. Valette
6
MPP-118
Include cross-check of BIS self-triggering in BIS IPOC module LHC I. Romera 2021-05-31
5
MPP-104
Discuss the final thresholds for collimators including BLM response between BLMTWG and the Collimation team LHC A. Lechner, B. Salvachua 2021-07-31
4
MPP-101
Finalize a list of commissioning steps for the BCCM LHC D. Belohrad
3
MPP-98
Communicate flag to be surveyed by the LHC SIS for the remote surveillance of the VME and cPCI creates to Jorg and agree on testing LHC N. Magnin, E. Carlier, J. Wenninger
2
MPP-93
Calculate magnets damage limits at 450 GeV and 7 TeV LHC Collimation, MPP
1
MPP-92
Review protection limit of inner triplet (80K) with realistic impact distributions LHC A. Lechner, MPP