160th SPS and LHC Machine Protection Panel Meeting¶
2018-03-16
Links¶
Indico¶
Minutes¶
EDMS¶
Topics and contributions¶
-
AOB - BLM threshold changes during for re-start after YETS 2017/18 (T. Medvedeva)
-
AFP & ALFA - changes during YETS 2017/18 and re-commissioning plans (S. Jakobsen)
-
Beam-beam wire collimators (TCTW): new interlocking electronics and proposed commissioning tests for existing and newly installed TCTW (A. Rossi)
-
MPS re-commissioning after YETs 2017/18: Collimation (B. Salvachua Ferrando)
-
AOB - all (D. Wollmann, J. Uythoven, J. Wenninger, M. Zerlauth, M. Valette)
-
CT-PPS - TOTEM - changes during YETS 2017/18 and re-commissioning plans (M. Deile)
Actions¶
Description | Responsible | Deadline | |
---|---|---|---|
29 | Send schematics of interlock to MPE to verify the interlock card and if re-testing is required LHC | A. Rossi |