176th SPS and LHC Machine Protection Panel Meeting¶
2019-03-29
Links¶
Indico¶
Minutes¶
EDMS¶
Topics and contributions¶
-
LRBB wire: results of failure-case study (B. Lindstrom)
-
New collimator temperature interlock logic (M. Di Castro)
-
AOB- all (D. Wollmann, J. Wenninger)
Actions¶
Description | Responsible | Deadline | |
---|---|---|---|
43 | Write commissioning procedure for the BBCW with and without beam, including reliable check of the wire polarities LHC | A. Rossi | |
42 | Measure delay time of the interlock chain for the BBCW, including a WIC unit, in case of a PC trip LHC | TE-MPE-MI | |
41 | Write specification for the temperature interlock logic and the filtering of the unphysical temperature sensor readings in the LHC collimator jaws and cooling circuits, and implement them after acceptance LHC | M. Di Castro, EN-SMM | 2021-06-30 |