244th Machine Protection Panel Meeting (LHC)¶
2024-03-08
Links¶
Indico¶
Minutes¶
EDMS¶
Topics and contributions¶
-
Updates and status on the MPS commissioning checklists (C. Hernalsteens, M. Gasior, Y. Dutheil)
-
LBDS test mode: implementation and validation (C. Boucly, N. Magnin)
-
Intensity ramp-up proposal (C. Wiesner)
-
Minutes and actions (D. Wollmann)
-
Readiness for first beam (A. Butterworth, B. Salvachua Ferrando, C. Zamantzas, D. Mirarchi, G. Pigny, J. Wenninger, M. Trzebinski, M. Deile, M. Saccani, R. Secondo, Y. Dutheil)
Actions¶
Description | Responsible | Deadline | |
---|---|---|---|
218 | BI will trigger the necessary actions with the BIS team after they deploy the latest firmware LHC | M. Gasior, BIS Team |