2024¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-247 COLLWG |
Displaced BLMs in IR7 - Thresholds, response, sensitivity and first experience during scrubbing and the intensity ramp-up (B. Salvachua Ferrando, C. Zamantzas, S. Morales Vigo) |
blm-thresholdsblm-ir7 | |
MPP-246 |
Readiness for first Stable Beams (A. Butterworth, B. Salvachua Ferrando, C. Zamantzas, D. Mirarchi, F. Van Der Veken, G. Pigny, I. Romera Ramirez, J. Wenninger, M. Trzebinski, M. Deile, M. Saccani, R. Secondo, Y. Dutheil) |
stable-beams-readiness | |
MPP-244 |
Readiness for first beam (A. Butterworth, B. Salvachua Ferrando, C. Zamantzas, D. Mirarchi, G. Pigny, J. Wenninger, M. Trzebinski, M. Deile, M. Saccani, R. Secondo, Y. Dutheil) |
stable-beams-readiness |
2023¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-242 |
AOB: Installation of additional BLMs and replacement of 6 SEMs by LICs in the collimation region | blm-ir7 | |
rMPP | Beam Loss Monitor system |
2022¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-226 |
Readiness of Machine Protection and related systems for a full machine at injection (scrubbing) and things open before taking a 12 bunch train up to top energy. | stable-beams-readiness | |
MPP-223 |
Status of MP system commissioning before first beam | stable-beams-readiness |
2021¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-214 |
Status MP system commissioning before first injection of a nominal bunch | stable-beams-readiness | |
MPP-212 |
Status of BLM testing with TIM and proposal for sub-set of tested BLMs before the pilot beam test | blm-hardware | |
MPP-207 |
Re-commissioning of the BLM System | blm-hardwareblm-software |
2020¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-200 |
Overview and architecture | pspsblinac4 | |
MPP-192 |
Introduction BLM related activities during LS2 in the injectors | blm-hardwareblm-software |
2019¶
Reference | Title | Tags | Links |
---|---|---|---|
Workshop | Beam loss monitor system |
2018¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-161 |
MPS re-commissioning after YETS 2017/18: BLM System | lhc-revalidationblm-hardware |
2017¶
Reference | Title | Tags | Links |
---|---|---|---|
AOB: HV problem at BLMs R3 - observations and possible mitigations - TBC | blm-hardware | ||
MPP-144 |
BLM System: Summary of changes and re-commissioning after EYETS | blm-hardwareblm-software |
2016¶
Reference | Title | Tags | Links |
---|---|---|---|
Beam Loss Monitors and Diamond detectors: Configurations and interlock logic | linac4 |
2015¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-118 |
Review injection BLM interlock inhibit | blm-hardwareblm-software | |
MPP-106 |
BLM system summary of commissioning results (B. Dehning, C. Zamantzas) |
blm-hardwareblm-software | |
MPP-105 |
Round table discussion on MPS commissioning status | lhc-revalidation |
2014¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-99 |
Technical implementation of BLM interlock inhibit during beam injections | blm-hardware |
2013¶
Reference | Title | Tags | Links |
---|---|---|---|
Workshop | Hardware changes in BLM system during LS1 |
2011¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-55 |
Changes of BLM system for 2012 run | blm-hardwareblm-software | |
MPP-51 |
LHC BLM system: possible modification schemes to KEEP or to FORCE true the beam permit signal at injection | blm-software | |
MPP-47 |
Summary of BLM Review | blm-hardwareblm-software |
2009¶
Reference | Title | Tags | Links |
---|---|---|---|
MPP-18 |
BLM results from injection test | blm-hardwareblm-software |
2006¶
Reference | Title | Tags | Links |
---|---|---|---|
MPWG | Beam Loss Monitor electronics and beam dump thresholds | blm-hardwareblm-thresholds |
2004¶
Reference | Title | Tags | Links |
---|---|---|---|
MPWG | LHC Beam Loss Monitors - design of the digitial electronics | blm-hardware |