Skip to content

Past topics

2024

Reference Title Tags Links
MPP-243
2024 machine revalidation strategy
(F. Van Der Veken)
lhc-revalidation

2023

Reference Title Tags Links
MPP-234
2023 machine revalidation strategy
(F. Van Der Veken)
lhc-revalidationloss-maps

2018

Reference Title Tags Links
MPP-168
AOB: Required revalidation after TS2: loss maps, asynchronous dump tests, intensity ramp-up etc
(C. Bracco, D. Wollmann, J. Uythoven, R. Bruce, S. Redaelli)
lhc-revalidation
MPP-165
AOB: Re-validation requirements after TS1 - TBC
(N. Fuster Martinez, S. Redaelli)
lhc-revalidation
MPP-161
AOB: Proposal for machine protection envelope during the Easter WE
(J. Wenninger)
lhc-revalidation
MPP-161
MPS re-commissioning after YETS 2017/18: SIS
(J. Wenninger)
lhc-revalidationsis
MPP-161
Proposal for intensity ramp-up and check list after YETS 2017/18
(D. Wollmann)
intensity-ramp-uplhc-revalidation
MPP-161
MPS re-commissioning after YETS 2017/18: BLM System
(C. Zamantzas)
lhc-revalidationblm-hardware
MPP-160
AOB - BLM threshold changes during for re-start after YETS 2017/18
(T. Medvedeva)
lhc-revalidationblm-thresholds
MPP-160
AFP & ALFA - changes during YETS 2017/18 and re-commissioning plans
(S. Jakobsen)
lhc-revalidation
MPP-160
MPS re-commissioning after YETs 2017/18: Collimation
(B. Salvachua Ferrando)
lhc-revalidationcollimation
MPP-160
CT-PPS - TOTEM - changes during YETS 2017/18 and re-commissioning plans
(M. Deile)
lhc-revalidation
MPP-159
MPS re-commissioning after YETS 2017/18: Vacuum System
(G. Pigny)
lhc-revalidation
MPP-159
MPS re-commissioning after YETS 2017/18: BIS/SMP
(I. Romera Ramirez, R. Secondo)
lhc-revalidation
MPP-158
MPS re-commissioning after YETS 2017/18 - Injection Protection / LBDS
(C. Bracco)
lhc-revalidation
MPP-158
AOB: MPS re-commissioning planning overview
(D. Wollmann, M. Zerlauth)
lhc-revalidation
MPP-157
AOB: MPS re-commissioning planning overview - M. Zerlauth / D. Wollmann
(D. Wollmann, M. Zerlauth)
lhc-revalidation
MPP-157
PIC/WIC/FMCM YETS activities & Re-commissioning plans
(A. Antoine)
lhc-revalidation

2017

Reference Title Tags Links
MPP-148
Review of MPS readiness for unsafe beam / trains
(D. Wollmann, J. Uythoven, M. Zerlauth)
lhc-revalidation
MPP-146
MPP proposal for 2017 intensity ramp-up and update of intensity increase check list template
(D. Wollmann)
mps-checklistintensity-ramp-uplhc-revalidation
MPP-146
Overview of MP system re-commissioning requirements with beam
(M. Zerlauth)
lhc-revalidation
MPP-142
WIC: Summary of changes and re-commissioning after EYETS
(R. Mompo)
lhc-revalidationwic
MPP-142
PIC: Summary of changes and re-commissioning after EYETS
(A. Antoine)
lhc-revalidationpic
MPP-142
BIS: Summary of changes and re-commissioning after EYETS
(C. Martin)
lhc-revalidationbis
MPP-142
FMCM: Summary of changes and re-commissioning after EYETS
(I. Romera Ramirez)
lhc-revalidationfmcm
MPP-142
SMP: Summary of changes and re-commissioning after EYETS
(I. Romera Ramirez)
lhc-revalidationsmp
MPP-140
AOB - Update on re-commissioning of MP Systems after EYETS
(D. Wollmann)
lhc-revalidation
MPP-139
AOB - Re-commissioning of MP Systems after EYETS
(D. Wollmann, M. Zerlauth)
lhc-revalidation

2016

Reference Title Tags Links
MPP-128
COLLWG
AOB: Discussion on system validation after technical stop
(D. Wollmann, J. Wenninger, M. Zerlauth, M. Valette, R. Bruce, S. Redaelli)
lhc-revalidation
MPP-123
Status of MPS commissioning after YETS 2015/16
(D. Wollmann, M. Zerlauth)
lhc-revalidation
MPP-121
MPS re-commissioning for 2016 - a first look
(D. Wollmann, M. Zerlauth)
lhc-revalidation

2015

Reference Title Tags Links
MPP-110
Summary of the MP Workshop on readiness of the Machine Protection Systems for MJ beams
(M. Zerlauth, R. Schmidt)
lhc-revalidation
MPP-105
Round table discussion on MPS commissioning status
(C. Bracco, C. Martin, C. Zamantzas, E. Holzer, E. Holzer, G. Valentino, G. Pigny, I. Romera Ramirez, J. Uythoven, J. Wenninger, M. Zerlauth, S. Gabourin, W. Bartmann)
lhc-revalidation
MPP-101
MPS commissioning plan
(M. Zerlauth)
lhc-revalidation

2013

Reference Title Tags Links
MPP-84
Update of (Re-)Commissioning procedures for PIC, FMCM, BIS, ...
(D. Wollmann, J. Wenninger, M. Zerlauth)
lhc-revalidation

2010

Reference Title Tags Links
MPP-24
MPS tests with beam (450 GeV)
(J. Wenninger)
lhc-revalidation

2009

Reference Title Tags Links
MPP-17
Collimator commissioning plan
(R. Assmann, R. Assmann)
collimationlhc-revalidation
MPP-10
Time estimates for MPS tests with beam
(J. Wenninger)
lhc-revalidation
MPP-7
MPS commissioning phases
(J. Wenninger)
lhc-revalidation

2005

Reference Title Tags Links
MPWG Commissioning MPS - Strategies for Commissioning LHC MPS
(R. Schmidt)
lhc-revalidation